SSH EN 62382:2013

Sistemet e kontrollit për proceset industriale - Kontrolli i nyjeve te qarqeve elektrike dhe instrumenteve

Control systems in the process industry - Electrical and instrumentation loop check
24 pri 2014

General information

60.60     10 shk 2014

DPS

DPS/KT 6

European Norm

25.040.40  

anglisht  

Buying

Publikuar

Language in which you want to receive the document.

Scope

IEC 62382:2012 describes the steps recommended to complete a loop check, which comprises the activities between the completion of the loop construction (including installation and point-to-point checks) and the start-up of cold commissioning. This standard is applicable for the construction of new plants and for expansion/retrofits (i.e. revamping) of E&I installations in existing plants (including PLC, BAS, DCS, panel-mounted and field instrumentation). This second edition cancels and replaces the first edition published in 2006 and constitutes a technical revision. The main changes with respect to the previous edition are: The definition of the documents mentioned in the standards is in accordance with IEC 62708: Documents for Electrical and Instrumentation Projects in the Process Industry. Subclause 6.3 has been revised.

Life cycle

PREVIOUSLY

WITHDRAWN
SSH EN 62382:2007

NOW

PUBLISHED
SSH EN 62382:2013
60.60 Standard published
10 shk 2014

REVISED BY

IN_DEVELOPMENT
prSSH EN IEC 62382:2024

Related project

Adopted from EN 62382:2013